List of work packages CLIC Experimantal Verification:
| Work package | Work package holder | |
| CTF3 Consolidation & Upgrades | F. Tecker | |
| Drive Beam phase feed-forward and feedbacks | P. Skowronski | |
| TBL+, X-band high power RF production & structure testing | S. Doebert | |
| Two-Beam module string, test with beam | W. Farabolini | |
| Drive-beam front end facility | S. Doebert | |
| Modulator development | D. Nisbet | |
| Drive Beam Photo-Injector | C. Hessler | |
| Low Emittance Ring tests | Y. Papaphilippou | |
| Accelerator Beam System Tests (ATF, FACET,…) | R. Tomas |